Further updates have been given on several planned railway stations in the Bristol region. A total of 11 stations in our region are in a rail network blueprint for 2050, published by leaders from across South Wales and England.
The group of leaders, under a partnership called the Western Gateway Partnership, aim to correct a lag in the area’s rail transport compared to other regions in the UK by increasing capacity and services. In a ‘vision’ network map they have included a list of new stations in the Bristol region, with each given a level of progress; aspirational or committed.
And work is now taking place on Ashley Down with opening dates given for Henbury and Filton, which are both part of the Henbury Spur.
Meanwhile, for campaigners behind stations like Saltford and St Anne’s Park, the Western Gateway Partnership publication will give comfort that the schemes are still under consideration. The same goes with Pilning, where passengers can currently get services only in one direction, and only on a Saturday.
And for stations like Pill and Portishead, the document reaffirms the commitment by the region’s leaders to see the projects out. Here’s the list of stations included in the document - called ‘2050 vision to transform rail for South Wales and Western England’ - which can be seen in detail here.
Here are the 11 stations, and updates on the progress of each:

5. Portishead - Committed (expected opening 2026)
The opening of Portishead station forms under Phase 1b of the MetroWest project. Although there are challenges still ahead, the project got planning consent from the Department for Transport in November last year. It will see the railway line to Bristol reopened with journeys expected to take just 23 minutes. A full business case is currently been drawn up ahead of work starting. | WECA

6. Pill Railway Station - Committed (expected opening 2026)
Pill, like Portishead, also comes under Phase 1b of the MetroWest project - and like its neighbour is expected to open in three years time with the reopening of the railway line. Pill’s station closed in 1964 and had two platforms. Under reopening, trains to and from Portishead will use the southern platform, which will be resurfaced and provided with a shelter. The northern platform will not be brought back to use. | WECA

7. Ashton Gate - Aspirational [paused]
Inclusion of Ashton Gate will be welcomed - however, the project has been ‘paused’ according to the 2050 vision. Locals and councillors will hope there will be movement again on the project with space left for the potential new station next to the Alderman Moore Allotments site. Bristol City Council say the station, on the Portishead line, could also serve a 510-home estate called Longmoor Village in Ashton Vale. | Bristol Archive

8. Portway Park and Ride - Committed (expected opening 2023 summer)
Portway Park & Ride will be the first new railway station in Bristol - and will come under Phase 1a of the MetroWest programme. The station in Shirehampton will see trains run half hourly along the Severn Beach line, running through the city. The station lies next to an existing park and ride, and has cost just over £4 million to build, with plans stretching back over a decade. Pictured is Councillor Don Alexander, Bristol City Council’s Cabinet Member for Transport, at the site of the new station. | Network Rail