Fresh delay for Bristol's River Avon flood defences despite rising risk to 30,000 homes
Construction of major new flood defences along the River Avon in Bristol won’t begin for at least another five years. Last autumn an engineering company was hired to design the flood defences although questions remain about how the huge cost of building them will be paid for.
Bristol City Council has appointed Jacobs UK to draw up plans for the Bristol Avon Flood Strategy, which has now been rebranded as Avon Riversides 2100. The defences will take seven years to build and should protect the city from rising sea levels due to climate change.
A funding strategy has still not yet been developed, with the defences expected to cost around £250 million to build. And a lack of detailed updates about the flood defences was criticised during a meeting of the member forum on Tuesday, January 13.


Green Councillor Patrick McAllister, representing Hotwells and Harbourside, said: “We should probably look to improve our public consultation and communication on this issue. It’s an issue that a lot of my ward residents are particularly engaged with.”
By the end of the century 30,000 properties in Bristol could be vulnerable to flooding. Critical infrastructure like roads and train stations could be affected by higher tides and stronger storms, and the city’s transport network could be severed by flooding, according to previous council reports. The primary threat is from tidal flooding, expected to grow as polar ice sheets melt.
The plans include building nine miles of flood defences along the Avon from Swineford to the east of Bristol, through the city centre and up to Shirehampton. The council is working with the Environment Agency and the West of England Combined Authority to get them built. Construction was initially expected to begin next year, but now won’t start until the next decade.
Liberal Democrat Cllr Andrew Brown, chair of the economy and skills policy committee, said: “We are now in contract with Jacobs and work has been progressing well in mobilising the new team and facilitating a smooth transition from the previous phase of the project.
“A funding strategy has been developed that explores a range of feasible scenarios to finance the construction phase, which will be developed further as the full business case is progressed. Our current programme shows an earliest possible construction start in 2030/31, while opportunities for quick wins and third party delivery opportunities will be continually explored.”
Councillors previously heard suggestions that the flood defences should be named after BP and Shell, due to their role in causing the climate to heat up. The new defences are needed because of the growing risk of severe flooding to Bristol, as sea levels will rise and storms get far worse. High tides and severe storms can combine to cause storm surges, which would be devastating.